Construction on Highway 20 and Memorial Trail roundabout in Sylvan Lake starting soon

Apr 19, 2024 | 4:33 PM

Town of Sylvan Lake PSA — Construction on the roundabout is beginning soon. When phase 1 begins, the intersection will become a right in right out only. This change along with detours is tentatively scheduled for May 6. Please plan for alternate routes. Thanks in advance for your patience and kindness with the construction workers and other drivers navigating the changes.

Phase 1: Dates TBD

Starting April 22

  • Hydro vacuum work on underground crossings

Expected early May

  • Memorial Trail may require full closure for up to 2 days at certain times
  • Fortis line move
  • No left turns:
    • From Highway 20 northbound lane onto westbound Memorial Trail
    • From Highway 20 southbound lane onto eastbound Township Road 384
    • From Memorial Trail eastbound lane onto northbound Highway 20
    • From Township Road 384 westbound lane onto southbound Highway 20

Phase 2: Dates TBD, expected start mid June, 2024

  • Township Road 384 CLOSED at Highway 20
  • Memorial Trail may require full closure for up to 2 days at certain times
  • No left turns:
    • From Highway 20 northbound lane onto westbound Memorial Trail
    • From Highway 20 southbound lane onto eastbound Township Road 384
    • From Memorial Trail eastbound lane onto northbound Highway 20

Ask & Answered

Open House

(Town of Sylvan Lake PSA)