Red Deer city council approved first reading of four borrowing bylaws that authorize up to $5.41 million for approved 2027 capital projects.

If second and third reading is approved, the proposed borrowing would fund several items, including installing 1,400 metres of water main to support water distribution for $310,154.

It would also fund a lift station near Highway 11A for $462,150 to support future development in the area.

In addition, over $4.1 million to advance detailed design and some construction for an Indigenous Culture Centre. The centre is intended to be developed with Indigenous communities.

Finally, if approved, $526,851 would be dedicated to rehabilitation and replacement work at civic facilities, including emergency services facilities.

The city says these projects have a combined budget of $6.81 million, with approximately $1.40 million funded from reserves and the remainder proposed through borrowing.

Borrowing for the water main and lift station would be repaid through offsite levies, while municipal property tax revenue would serve as a backup repayment source.

Borrowing for the Indigenous Cultures Centre and civic facility preservation would be repaid through municipal property tax revenue.

The proposed maximum borrowing terms are 20 years for the water main, lift station and civic facility preservation projects, and 30 years for the Indigenous Cultures Centre.

Passing first reading allows the city to advertise the proposed borrowing and give residents an opportunity to respond and comment on the borrowing bylaw before council considers final approval at a later date.

The proposed bylaws will be later considered on November 5 and November 12, 2026. The deadline to submit a petition to the city is November 27.

Once the advertising requirements and process are complete, the bylaws can return to council for second and third readings, which is scheduled to take place on December 8.

If the bylaws receive final approval, the city would borrow only as needed to cover project costs. Borrowing could occur over several years, and they would not be required to borrow the full authorized amount.