Capital plan stresses need for repairs at Hunting Hills High School
Red Deer Public Schools has submitted its Three Year Capital Plan for 2020-2023 that has been updated in order to address growing concerns surrounding Hunting Hills High School, namely the roof, mechanical and electrical issues.
An addition to the school is also being sought to create room to accommodate an additional 200 students. Hunting Hills is currently operating at 98 percent capacity (1478 students) and officials are expecting that to grow by another 173 students by 2023.
The total cost of a modernization of Hunting Hills High School would be around $7 million.
When the board was approached with the concerns surrounding the building they initially thought it could be handled it through Infrastructure Maintenance and Renewal (IMR) funds, but it was quickly discovered that the repairs would cost much more than they could afford.