RED DEER- Construction of the 67 Street and Johnstone Drive/Orr Drive roundabout continues throughout the summer.
Work that is taking place over next two weeks (July 31 to Aug. 12) includes the following:
– Road reconstruction on 67 Street, between Golden West Avenue and the roundabout
– Paving on parts of 66 Street, Orr Drive, Johnstone Drive and 67 Street
– Permanent pavement markings
– Permanent street lighting
– Asphalt trails
– Landscaping of boulevards and roundabout circles
– Completion of Concrete Paving on 67 St.
– Landscaping on 66th / Orr Drive roundabout.
– Asphalt trails on 67th Street and on Orr Drive.
– Curb and Gutter and medians on 67th St West of roundabout.