QE 2 / Gaetz Avenue Interchange update:
RED DEER- With construction of the new southbound access to the QE 2 underway, permanent closure of the frontage road along Gasoline Alley West (between the businesses and the QE 2) will take place this week (weather dependent).
Access to all businesses along Gasoline Alley West will be maintained via Leva Avenue.
This closure will result in some traffic pattern changes:
– In the short-term, southbound access to Gasoline Alley West will be provided directly from the QE 2 through the Leva Avenue roundabout.
– Permanent access to Gasoline Alley West will be provided via a new collector-distributor road currently under construction.